| Indian School Road Improvements - Phase 1 & 2 Project Owner: City of Scottsdale This project included the phased street and utility improvements of Indian School Road (Drinkwater Boulevard to Pima Road). Wet utility construction involved miscellaneous water line and service relocations, general drainage modifications, and 3,800 LF of large diameter storm drain piping. Work on Phase 1 was from Hayden Road to Pima Road and Phase 2 was from Drinkwater Boulevard to Hayden Road.
|
||||||||||||

Letter from Sun Eagle Corporation about Achen-Gardner Construction's work on the project.




