Sanitary Sewer and Southern Avenue Interceptor Rehabilitation  

Project Owner: City of Mesa
Project Type:
Construction Manager at Risk
Construction Dates: 05/08 to 10/08

This City of Mesa project required the rehabilitation of wastewater piplines at five different segments. These segments included 16,300 LF of 12-to-21-inch sanitary sewer using CIPP and the sliplining rehab of 2,600 LF of 27-inch and 7,900 LF of 20-inch sanitary sewer. Work also included the rehabilitation of 46 manholes.